Rail Transit Jinhua-Yiwu Section Countdown!
轨道交通金义段开通初期运营倒计时!

发布时间: 2022-08-23

On August 15, Jinhua-Yiwu section of Jinyi East urban rail transit project successfully passed the completion acceptance, which marks the countdown of the initial operation of Jinhua-Yiwu section has started.

The acceptance of urban rail transit construction projects is divided into three steps: unit acceptance, construction acceptance and completion acceptance. Completion acceptance will be realized after construction acceptance and before the initial operation, combined with the trial operation effect, it refers to the acceptance to confirm whether the construction project meets the design objectives and concrete requirements.

After successfully passing the completion acceptance, Jinhua-Yiwu section will soon face the safety assessment test before the initial operation, and then the initial operation can be realized.

The total length of Jinhua-Yiwu section is about 58.4 km, with 17 stations along the line, including 6 underground stations and 11 elevated stations. The line starts from Jinhua station and ends at Yiwu Qintang station.